Chris Binnington is a director of the Association of Arbitrators (Southern Africa (NPC) and a Life Fellow of the Association of Arbitrators. He was, from 1997 to 2010, the Chairman of the Association, and is widely regarded as one of the most experienced adjudicators in South Africa. He has presented numerous training courses on the process of adjudication and has assisted a number of organisations to set up panels of adjudicators. He is also a director of “Binningtons engineering and construction contract consultants” offering commercial and contractual advice to employers, contractors and sub-contractors in the construction industry.

DEALING WITH DEFAULTING LOSERS IN ADJUDICATIONS  

Introduction 

One of the weaknesses of the adjudication process in South Africa is the absence of an effective enforcement  process. In the United Kingdom, applications for enforcement are made to the Technology and Construction  Court (TCC) a division of the Queen’s Bench Division (QBD). 

The TCC, as the name implies, is a specialist court with specialist judges who deal with all types of construction,  engineering and technology disputes both within the UK and which arise internationally. In particular the court  deals with enforcement of or challenges to adjudicators’ decisions arising out of the Housing Grants,  Reconstruction and Regeneration Act 1996 (HGRRA) (as amended).  

As a consequence, the court has become adept in matters relating to adjudicators’ decisions and the enforcement  thereof or the setting aside of such decisions. It is also possible to obtain a court order handed down by the TCC  within a matter of a few weeks of application which, in turn, results in the rapid enforcement of an adjudicator’s  decision thus lending efficacy to the entire process. 

Obviously, this is only in respect of matters to which the HGRRA applies, and thus is of no application to  construction disputes in South Africa. 

The South African Situation 

Where enforcement of an adjudicator’s decision becomes necessary in a construction dispute subject to the law  of South Africa, it will be necessary to approach the High Court having jurisdiction, on a motion application, that  is by way of notice of motion accompanied by a founding affidavit, and such application will be heard by  whichever judge is allocated on the day. The probability is that the judge will have little or no experience of  construction disputes and may be wholly unfamiliar with the adjudication process. What makes the court  application even less attractive is that there are unlikely to be circumstances to warrant urgency and the  application will thus go on to the normal motion roll and may take several months before the matter comes  before the court. 

It is now settled law in South Africa that an adjudicator’s decision is immediately binding and save for those rare  occasions when an adjudicator has given a decision for which he lacks authority, or has committed a gross  procedural error, the decision should be enforced regardless of whether the decision he or she has come to is  correct in law or has been made as a consequence of a misinterpretation of the facts as presented.[1] 

However, for the reasons I have set out above, the nett effect of this unwieldy and slow court process is that the  adjudication process is rendered ineffective where the losing party elects to withhold the payment immediately  due upon receipt of the adjudicator’s decision.  

A Possible Solution 

I would like to suggest the following as a possible solution to the problem.  

In most of the standard forms of contract currently in use in South Africa, a dissatisfied party may open the door  to review by the Tribunal, which is generally by arbitration. The process is to give a Notice of Dissatisfaction within the period specified by the contract. This will not interfere with the immediately binding nature of the  decision but merely open the door to having the dispute heard afresh (de novo) by an arbitrator. Defaulting  parties will thus attempt to delay the enforcement proceedings arising from the adjudicator’s decision as long as possible in the hope that they will get a more favourable result from an arbitrator before the court enforces the  adjudicator’s decision.

This tactic could be eliminated if a small amendment is made to the governing construction contract to the effect  that, once a Notice of Dissatisfaction has been issued, no further steps shall be taken to proceed to arbitration  until such time as the defaulting party has made payment in full in accordance with the adjudicator’s decision. 

Of course, this will not prevent a defaulting party from delaying payment and simply allowing the enforcement  proceedings to take place. It will however place a significant barrier in place to delay the onset of arbitration  proceedings and therefore to ultimately delay the possibility of a reversal of the findings of the adjudicator by an  arbitrator. 

CHRIS BINNINGTON Pr Eng 

Director 

ASSOCIATION OF ARBITRATORS (SOUTHERN AFRICA) NPC


[1]   Ekurheleni West College v Segal and Another (1287/2018) [2020] ZASCA 32 (2 April 2020)